Bulmers Cider Factory

Main Contractor: Chalcroft Ltd.

K.F. Quinn were appointed by the main contractor of this high profile project, to carry out all of the reinforced concrete works throughout the project.

The contract consisted of in excess of 5000m² of reinforced concrete floor slabs to the new bottling plant / warehouse and also the new process building. We also carried out extensive works to form new silo foundations, pump house bases, tank bases and bund walls and plinths.

Suspended roof slabs were also constructed to various buildings such as pump houses, sub stations and engineering workshops.

All of these works were carried out within a live working environment, in which the clients operations could not be interfered with, so therefore concrete pours were programmed to suit allocated time slots, excessive un-sociable hours and weekend working was required to carry out these works successfully.

This works package was carried out on a full supply basis in excess of £500,000.